Contractor Initiated Compensation Events

The following Contractor-initiated Compensation Related communications are recorded in AssetWise:

When a Contractor initiates and issues a Notification of Compensation Event as a result of an Early Warning Notification (EWN), the following occurs:

  • Contractor initiates and issues a Notification of Compensation Event (CNCE) form
  • Project Manager initiates and issues a reply, on the Project Manager's Response Notification (PMRN) communication, and a draft Project Manager's Implemented Compensation Event Notification (ICE) is created automatically
  • If a quote is required, then the Project Manager initiates and issues an instruction to submit quotations, on the PMIQ communication
  • Contractor is allowed three weeks to prepare and submit the quotation on the CQT communication
  • Project Manager is allowed two weeks to issue a reply to the quotation on the PMRQ communication
  • If the quotation is past due, the Contractor receives a Notification of Late Response reminder (CCM)
  • If an extension is required for the quotation, the Project Manager notifies the agreed extension of the period of time for a response to be received, via the EXT communication
  • Project Manager issues Notification of Assessment (PMA) within three weeks
  • Project Manger issues Notification of Implemented Compensation Event (ICE)

The workflow for issuing a Contractor Initiated Compensation Event is as follows:

Note: * Denotes a three stage workflow: Initiate > Review > Issue.
Note: ** Denotes a five state workflow: Initiate > Review > Assign Action > Close Out.